In Runn, one project can only have one consistent project rate for each role over the entire duration of the project. We suggest creating a new project for each year, so you can customize the project rate.
If you would like to report on the metrics of the overall project (summing up multiple years):
Create a Single Select Project Custom Field and add the internal Project ID or Project Name as an option
Add the same internal Project ID/ Project Name custom field to the projects of different years. In the example below, the internal Project ID, A1234 is added under the "Parent Project" custom field:
On the Project Planner, you can group by the custom field to group these projects together:
In reports, add the custom field as a grouping, and you can view the overall project budget, revenue and cost across multiple years: