Workload is calculated by using this formula:

Sum of Confirmed assignment hours for people

+

Sum of Tentative assignment hours for people

+

Sum of Confirmed assignment hours for placeholders

+

Sum of Tentative assignment hours for placeholders

=

Total workload

PLEASE NOTE THAT ASSIGNMENTS FOR THOSE WITH NO CONTRACT WILL STILL COUNT - SO CONSIDER TRANSFERRING THESE TO A PLACEHOLDER OR EXTENDING THE CONTRACT FOR BETTER VISIBILITY ON TRUE WORKLOAD.