Only Admin users with Edit Account Settings and Data set as On can access the CSV Import/Exporter.
You can use the Assignment CSV Import/ Exporter to:
Import new assignments for people and placeholders on projects
Export assignments for both active and archived projects under a customized date range
Update some properties of the assignments (explanation below)
Placeholders must be created manually or via the Placeholder CSV before adding assignments to them.
You cannot change an existing assignment's Project Role, Workstream or Phase. You will have to change it manually in Runn.
You cannot delete existing assignments through the CSV Importer. You will have to delete the assignments manually in Runn.
You can click on the Table of Contents on the right to jump to any section anytime.
Adding new assignments
1. Downloading Template
Hover your cursor to the top right-hand corner, click Settings
Click CSV
Click on the Assignments Tab
Click Download Template CSV
You will see some samples from the template for your reference. You can remove them and add your actual data to the file.
2. Preparing your data in the CSV file
Data Format and Requirements
Refer to the Data Format and Requirements section to prepare your data.
Here are some points to note:
Column headers
It is recommended that the column header names stay the same as those you see in the file downloaded from Runn
Can I use my own column header names in my CSV file?
Yes. We understand that each organization or system may have different naming conventions, and it might be more convenient to just import the file as is.
Our CSV tool allows you to match the column headers into Runn's format with just a few clicks. See the help article here.
Remove Optional columns if you don't need it
If the field is marked as optional and you don't need to import data against it, you can delete the column entirely from your spreadsheet.
Importing a file without the optional column will not delete any data in Runn
Where to find the Project ID?
Refer to the Import/ Export Projects help article to learn how to export Phase IDs.
Where to find the Existing Phase ID?
Refer to the Import/ Export Phases help article to learn how to export Phase IDs.
Remove all unrequired columns
If you have other columns on your spreadsheet that are not listed in the downloaded CSV file, please remove all these columns before importing
3. Importing assignments
Jump to the Importing CSV file in Runn section and follow the steps to import your CSV file.
Updating/ Exporting Assignments
If your account already has assignments and you want to add new assignments or update existing data, you can easily download the existing assignments, make the changes, and re-import the CSV file to Runn.
What you can update
Similar to the assignment properties that you can edit in the Runn, you can update the following properties of an existing assignment:
Minutes per day
billable/ non-billable
Note
Shorten/ lengthen an existing assignment
You can shorten/ lengthen an existing assignment by adjusting EITHER the assignment's Start Date or End Date.
If you change the Start Date in the CSV file, you must keep the End Date the same.
If you change the End Date in the CSV file, you must keep the Start Date the same.
Do not change BOTH the start date and end date of an assignment. This may create new assignments unexpectedly.
You cannot reschedule an assignment via the CSV Tool.
What you cannot update
You cannot transfer an assignment from one person to another person via the CSV Tool
You cannot reschedule an assignment to another time i.e. changing both the Start Date and End Date.
1. Exporting Existing Data
If you have assignments in Runn, you can export all assignments from here.
The assignments exported include both active and archived projects.
Hover your cursor to the top right-hand corner, click Settings
Click CSV
Click on the Assignments Tab
From the Export Assignments section, select a date range
Click Download Assignments CSV
What is the difference between the assignments exported from the CSV tab and the Export Tab?
The assignments exported from the CSV tab here are the same as those downloaded from the Export Tab, the difference is only the file format.
We continue to support the Export Tab as it is available for Managers with all financial data permissions, and the CSV importer is only accessible to admin users.
2. Preparing your data in the CSV file
Data Format and Requirements
Refer to the Data Format and Requirements section to prepare your data.
Here are some points to note:
Column headers
It is recommended that the column header names stay the same as those you see in the file downloaded from Runn. This way, Runn can automatically map the data into the system
Can I use my own column header names in my CSV file?
If it is more convenient for you to use your internal naming conventions in the column headers, it is also possible. You will have to manually match the data with a few clicks during the importing process
Our CSV tool allows you to match the column headers into Runn's format with just a few clicks. See the help article here.
Remove Optional columns if you don't need it
If the field is marked as optional and you don't need to import data against it, you can delete the column entirely from your spreadsheet.
Importing a file without the optional column will not delete any data in Runn
Where to find the Project ID?
Refer to the Import/ Export Projects help article to learn how to export Phase IDs.
Where to find the Existing Phase ID?
Refer to the Import/ Export Phases help article to learn how to export Phase IDs.
Remove all unrequired columns
If you have other columns on your spreadsheet that are not listed in the downloaded CSV file, please remove all these columns before importing
3. Importing the CSV file in Runn
Hover your cursor to the top right-hand corner, click Settings
Click CSV
Click on the Assignments Tab
Click Import Assignments CSV
4. Upload Assignments
Drag your file to the screen or click Import Assignments CSV
5. Matching the columns
On this screen, the items on the left are the column headers in your CSV file, while the items on the right are the column headers required in our CSV Tool.
If you haven't changed the column headers, they should be exactly the same. In this case, click Confirm
What do I do if the column headers are not the same?
Check out this help article to learn more.
6. Reviewing Entries
Carefully scroll through the page and check if all the information is correct.
❌ What to do if there is an error?
Check out this article to learn more about how to fix errors.
If everything looks good, click Complete Import
Congratulations! You have successfully imported assignments! 🎉
7. Validating the data
You can validate if the data are successfully uploaded by following the steps below: