Utilization is an important metric for assessing business and individual performance. It measures how many hours are allocated out of the total available work hours.

= Hours Allocated / Effective Capacity

  • Hours allocated - The total of all relevant assignments within a period

  • Effective capacity - The total available work hours. This is the total contracted capacity less any time-off.

In the utilization charts on the planner, you can see the non-billable utilization, billable utilization and total utilization across all resources in your organization, or a subset by using the filters.

Non-billable utilization = Total non-billable hours allocated / effective capacity

Billable utilization = Total billable hours allocated / effective capacity

Total Utilization =Total billable hours allocated + non-billable hours allocated / effective capacity


โ€‹

Metrics Example

Jo is contracted to work 40 hours per week (8 hrs per day).

This week:

  • Jo has 2 days off - one is a public holiday and one is scheduled leave. The rest of the week, Jo is booked 4 hrs per day on a billable project

  • Ash is contracted to work 20 hours per week (4 hrs per day). Ash is booked 2 hrs per day on a non-billable project

Contracted capacity

Time off

Effective capacity

Billable hours

Non-billable hours

Jo

40 hrs

8*2 = 16 hrs

24 hrs

4*5 = 20 hrs

0 hrs

Ash

20 hrs

0 hrs

20 hrs

0 hrs

2*5 = 10 hrs

Total

60 hrs

16 hrs

44 hrs

20 hrs

10 hrs

Non-billable utilization:

= Total non-billable hours allocated / effective capacity

= ( 10 hrs / 44 hrs ) * 100

= 23%

Billable utilization:

= Total billable hours allocated / effective capacity

= ( 20 hrs / 44 hrs ) * 100

= 45%

Total utilization:

= Total billable hours allocated + non-billable hours allocated / effective capacity

= ( (20 hrs + 10 hrs) / 44 hrs) * 100

= 68%

Notes:

  • Tentative projects are included in the utilization chart if the tentative project is within the filtered results and is toggled on in the planner

  • The planner and charts only show planned hours. Actuals logged in timesheets do not affect utilization there.