Calculations for Utilization Chart

Explanation of how we determine Utilization Chart metrics.

Updated over 3 weeks ago

In the utilization charts on the planner, you can see the non-billable utilization, billable utilization and total utilization across all people and placeholders in your organization, or a subset by using the filters.

Since the Chart is for forecasting purposes, the hours used for calculation based on scheduled hours only.

  • We recommend only viewing the Chart for a time period set in the future, not the past.

  • Actual hours on the timesheet are not used in the calculation on this Chart.

  • To obtain an accurate past utilization %, please refer to Reports.


Calculation

Metric Name

Description and Formula

Total Utilization % (on Utilization Chart)

Total Utilization % =

(Scheduled billable hours + Scheduled non-billable hours) / Effective capacity

  • Past scheduled hours added to placeholders are included in the calculation

Billable Utilization % (on Utilization Chart)

Billable Utilization % =

Scheduled billable hours / Effective Capacity

  • Past scheduled hours added to placeholders are included in the calculation

Non-billable Utilization % (on Utilization Chart)

Non-billable Utilization % =

Non-billable hours allocated / Effective Capacity

  • Past scheduled hours added to placeholders are included in the calculation


Example

Jo is contracted to work 40 hours per week (8 hrs per day).

This week:

  • Jo has 2 days off - one is a public holiday and one is scheduled leave. The rest of the week, Jo is booked 4 hrs per day on a billable project

  • Ash is contracted to work 20 hours per week (4 hrs per day). Ash is booked 2 hrs per day on a non-billable project

Contracted capacity

Time off

Effective capacity

Billable hours

Non-billable hours

Jo

40 hrs

8*2 = 16 hrs

24 hrs

4*5 = 20 hrs

0 hrs

Ash

20 hrs

0 hrs

20 hrs

0 hrs

2*5 = 10 hrs

Total

60 hrs

16 hrs

44 hrs

20 hrs

10 hrs

Non-billable utilization:

= Scheduled non-billable hours / effective capacity

= ( 10 hrs / 44 hrs ) * 100

= 23%

Billable utilization:

= Scheduled billable hours / effective capacity

= ( 20 hrs / 44 hrs ) * 100

= 45%

Total utilization:

= (Scheduled billable hours + scheduled non-billable hours) / effective capacity

= ( (20 hrs + 10 hrs) / 44 hrs) * 100

= 68%

Note:

  • Tentative projects are included in the utilization chart if the tentative project is within the filtered results and is toggled on in the planner