All Collections
Planner & Utilization Charts
Charts
Calculations For Availability Chart
Calculations For Availability Chart

How Availability Calculations are determined.

Lyssa Parisella avatar
Written by Lyssa Parisella
Updated over a week ago

The following is a guide on what the terms mean and how this data is calculated:

Max capacity: Sum of all people's hours - (minus) Sum of all time-off hours (Placeholders & No Contract NOT included)

Workload total: Sum of assignment hours for confirmed & tentative projects for BOTH people & placeholders (INCLUDES assignment hours for those with NO contract)

Availability: Max Capacity - (minus) Sum of Confirmed & Tentative Workload

Did this answer your question?