Runn calculates if your project is on track by looking at what work has been completed.
Because timesheets may be delayed or missing, Runn will automatically assume that the scheduled hours occurred until the actual value is entered.
If you are using Runn for time tracking, you should always enter the amount of actual time spent each day, including 0 if no work was done.