How do I compare the current project plan to a baseline?

Runn doesn’t currently have a built-in baselining feature that automatically compares your current plan to an original baseline.

However, there’s a simple workaround you can use to achieve this.


How can I create a baseline for comparison?

Before your project starts, you can create a snapshot of your plan by duplicating it:

  1. Duplicate your project

  2. Rename it (e.g. “Project X – Baseline”)

  3. Set the duplicated project as Tentative

This gives you a preserved version of your original plan that won’t affect reporting or utilization.


How do I compare the baseline with the current plan?

When you need to compare:

  1. Go to the Tentative toggle dropdown

  2. Turn on the baseline (tentative) project

  3. View it alongside your active project plan:
    ​

This allows you to visually compare:

  • Allocations

  • Timelines

  • Resource changes