Setting Up Project Budget: Budget by Phases

This budget method is available on Standard and Advanced Plans only.

Overview

Most suitable for customers who want to manage their budget across defined time frames (phases) and are not concerned with how those amounts are allocated by role. Ideal when phase-based tracking is key, but tracking by project roles isn’t required.

  • Budget is defined by project phases without assigning amounts to specific roles.

  • Available only for Time & Materials and Fixed Price pricing models

  • Suitable if you only need to define phase budgets by the monetary amount
    ​

❌ You cannot assign phase budgets by hours/ days. If you need to assign a budget by time, please choose Phases & Roles as the budget method.
​
❌ Not available for non-billable projects


Setting Up Project Budget: Budget by Phases

1. Add Phases on Planner

  • From the Project Planner, identify the project you would like to set up the budget

  • Before adding the budget, create the Phases from the Project Planner first
    ​


2a. Add Project Budget

  • From the Project Planner, identify the project you would like to set up the budget

  • Click on the 3-dot icon next to the Project Name and select Edit Budget

  • Select the desired Pricing Model from the dropdown.

  • For the Budget Method, select Phases
    ​

  • Add the total Project Revenue Budget to this field.
    ​

2b. Define Project Rates (optional)

  • By default, the Standard Rate Card is used (i.e. Default Role Rates). Skip this step if you are using the default role rates for this project

  • If you need to use another Rate Card, click on Project Rates Tab at the top right

  • Click on Standard (column header of the rates column) to choose another rate card
    ​

2c. Add Project Roles

  • Click on or stay in Project Rates Tab

  • Add the Project Roles from the dropdown menu
    ​


    ​

Can I change to another Rate Card or customize the Project Rates?

  • Yes! You can change the project rates at any time.

  • Pick another Rate Card, click on the grey arrow to apply the rates of the selected Rate Card
    ​

  • You can also customize the Project Rate per role by manually filling in the fields under the Project Rate column
    ​


3a. Add Phase Budget

  • Click on the Budget Tab

  • Fill in the Phase Budget per phase
    ​

❌ You cannot budget by hours using this Budget Method. If you need to budget by hours, use Phases and Roles as the Budget method instead.

3b. Check over- or underallocation

Once you have added the Phase Budget, Runn will flag you whether you have over- or under-allocated based on the total Project Budget.

Example

In the example above, the sum of Phase Budget equals Project Budget. Budget is fully allocated!


4a. Add Placeholders and Scheduled Hours on Planner

Once you've set up the Budget, you can start adding Placeholders and add scheduled hours (drag and drop assignments) from the Project Planner. Make sure the assignments are linked to a specific phase (the assignment should be in the same color as the associated phase).

⚡ Track budget remaining per phase easily

By default, Hours is the display unit for workload per role and per phase.

Click on Hours to open the dropdown menu. Switch to Revenue so you can see how much phase budget you are using when scheduling work. The figure will update in real-time as you add or remove assignments:
​

4b. Add Other Expenses (Optional)

  • If there are any non-labour expenses (Other Expenses), you can add them to the Other Expenses Tab

  • Enter the itemized expenses and associate them with the specific phases

  • The Charges will be tracked against the specific Phase Budget
    ​

❌ You cannot define an overall Other Expenses Budget using this Budget Method. When setting the Phase budget, please include the budget for other expenses items here.


5. Review Phase metrics from Project Dashboard

You can track the budget remaining for each phase from the Phases panel on the Project Dashboard:

For Time & Materials projects: Budget Remaining = Budget - Revenue

For Fixed Price projects: Budget Remaining = Budget - T&M Benchmark

(Note that you cannot view the T&M Benchmark figure per phase on the Phases panel. You can find the information in Reports)