How can I split 1 day of a resource into 2 different phases of the same project?
How can I split 1 day of a resource into 2 different phases of the same project?

Splitting a day assignment for the same resource on the same project- either to add notes or to assign to phases.

Lyssa Parisella avatar
Written by Lyssa Parisella
Updated over a week ago

In Runn, you can only add one assignment per day per resource per role on the same project. The way to get around this is to add them twice to the same project- but under different roles.

  1. Create a new role in Manage > Roles with the correct rates.

  2. Add the resource twice - once under each role.

  3. Create assignments for the resource under both roles and add details or assign to separate phases.

Here's a short video of how: