Time state
Other expenses don't impact the time view.
Revenue state
The charges of your other expenses affect the project performance (revenue) graph on the date they occur.
In the table below the graph, the other charges are laid out as follows:
Past - Other expense charges prior to today
Future - Other expense charges from today onwards
Total - Sum of other expense charges over the entire project duration
Budget - The budget you have set for other expenses

Cost state
The costs of your other expenses affect the project performance (cost) graph on the date they occur.
In the table below the graph, the other costs are laid out as follows:
Past - Other expense costs prior to today
Future - Other expense costs from today onwards
Total - Sum of other expense costs over the entire project duration
Budget - The budget you have set for other expenses