Performance Insight Dashboard

Track key metrics and performance indicators

Performance Insights

Compare planned work to actual outcomes, identify gaps, spot patterns of under or over-delivery, and analyze discrepancies to learn from past performance and enhance future forecasting.
​



​Scheduled vs Actual Project Workload

Comparison of scheduled allocations to actuals over time.

Because this is a line graph, make sure to select a time range of at least two weeks or two months for the data to appear.

Compare scheduled allocations vs actuals on projects over time, with a summary highlighting the total scheduled hours, actual hours, difference, and percentage deviation for the selected date range.

  • Switch workload type: View Total, Billable, or Non-Billable

  • Filter confirmed workload using the filters you are familiar with from the planner

  • Toggle the effort unit in display settings between FTE or Hours to adjust the y-axis

Calculation Information

  • Scheduled: Sum of hours scheduled on the Planner
    ​

  • Actuals: Sum of hours logged in timesheets
    ​

  • Difference: (Actuals - Scheduled)
    ​

  • Deviation: (Actuals - Scheduled) / Scheduled) x 100
    ​

⚠️ Future data is not available for this Insight.



​📈 Chart and Global Functions Overview: